Steam to Natural Gas Project update

Construction activities will affect four campus buildings this week.

January 13, 2020

Natural gas piping staged in construction area.Today through Saturday, Xcel Energy will install gas-service lines to the following buildings:

  • Boulder Creek
  • Science
  • PE/Event Center
  • Cherry Creek

Work will include open cutting for gas-line installation. While there are no planned service interruptions, the parking lot on the north side of Boulder Creek will be inaccessible as crews install new lines down Champa Street.

If you have any questions or concerns about this project, please contact Auraria Higher Education Center Facilities Services at 303-556-3260. Steam to Natural Gas Project updates are also available on the AHEC home page under Announcements.